$146,828
paid on this contract in FY2025
February 28, 2024February 27, 2029
Paid to
Efi Global Incprime contractor$635,274Paid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Airport fund · multi-year projects$146,828
Paid year by year, FY2025–FY2026
FY2026$488,446
FY2025$146,828
Type and award
Contract type: Construction
Award: Competitive bid
The project team
Efi Global IncPrime ContractorIdeal Restoration IncSubcontractor · LBE$334,232
Contract 1000032057 · Source: Supplier Contracts · every payment on this contract