CDM SMITH INC · AIR Airport Commission

San Francisco agreed $650,000 with CDM SMITH INC for contract 1000032324 (AIR Airport Commission); $248,933 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Agreed
$650,000
Paid
$248,933
38% of agreed
Remaining (calculated)
$401,067
The money
Paid against the agreed amount
Payments per fiscal year
2526
Largest year: $150,610 · dashed = fiscal year not closed yet

These bars total $300,955; the figure above is $248,933. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
April 1, 2024March 31, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
COMPETITIVE SOLICITATION

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
CDM SMITH INCPrime
APPLIED TECHNOLOGY & SCIENCE A-T-SLBESubcontractor$200,000
EFI GLOBAL INCSubcontractor$150,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)