Forklift training for the Public Utilities Commission

Original title: “PUC Forklist Training”

$17,581
paid on this contract in FY2025
$36,131 paid so far, of $129,580 agreed · runs to March 2030
March 15, 2024March 14, 2030
running

Contractor

Garig Equipment

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Public Utilities Commission fund · operating100%$17,581

Paid year by year, FY2024–FY2026

$8,348 in FY2024 · $17,581 in FY2025 (the highest) · $10,203 in FY2026

Click a year to see its amount.

Type and award

Contract type: Rents and other non-purchase agreements

Award: Rent or real estate

Next contract in this departmentEngineering services for transmission pipelines434th of 493 active contracts in this department by amount agreed$126,500