San Antonio Control Replacement Retrofit

BIG VALLEY ELECTRIC · PUC Public Utilities Commsn

San Francisco agreed $8.8M with BIG VALLEY ELECTRIC for contract 1000032410 (PUC Public Utilities Commsn); $7.0M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PUC SAN ANTONIO CTRL REPL RETR

Signed by Public Utilities Commsn

LBE
Agreed
$8.8M
Paid
$7.0M
80% of agreed
Remaining (calculated)
$1.8M
The money
Paid against the agreed amount
Payments per fiscal year
2526
Largest year: $3.9M · dashed = fiscal year not closed yet

These bars total $4.9M; the figure above is $7.0M. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
March 26, 2024May 14, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICES

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
BIG VALLEY ELECTRICLBEPrime
SINCLAIR GENERAL ENGINEERING CNSTR INCLBESubcontractor$773,976
PACIFIC ENGINEERING & CONSTRUCTION INCLBESubcontractor$200,000
PARC EnvironmentalSubcontractor$30,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)