Moccasin WWE treatment repair

Original title: “PUC Moccasin WWE Treatment Rep”

$2.1M
paid on this contract in FY2025
$4.5M paid so far, of $6.6M agreed · runs to January 2027
May 10, 2024January 6, 2027
running

Paid to

Sierra Mountain Construction Incprime contractor$4.5M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Hetch Hetchy power fund55%$1.1M
Water fund45%$934,763

Paid year by year, FY2025–FY2026

FY2026$1.8M
FY2025$2.1M

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

Sierra Mountain Construction IncPrime Contractor
Fusion Electric IncSubcontractor$1.1M
Pacific Engineering & Construction IncSubcontractor · LBE$400,000
C&N Reinforcing, Inc.Subcontractor · LBE$142,000
Mason PaintingSubcontractor$98,000