City loan for Sunnydale phase 3 infrastructure

Original title: “MYR Sunnydale Phase 3 Infra”

$8.0M
paid on this contract in FY2025
$22.4M paid so far, of $40.3M agreed · runs to November 2081
October 18, 2024November 4, 2081
running

Paid to

Sunnydale Phase 3 Infrastructure LLCprime contractor$22.4M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. A special revenue fund holds money earmarked for a purpose, often grants. The fund does not say where the money first came from.

Special revenue fund95%$7.6M
Special revenue fund · multi-year projects5%$394,583

Paid year by year, FY2025–FY2026

FY2026$13.9M
FY2025$8.0M

Type and award

Contract type: Grants the City gives out