Skip to main content

Municipal Transportation Agency

Transit agency contract 2024-20 (FTA)

Original title: “SFMTA-2024-20-FTA”

$1.5M
paid on this contract in FY2025
$9.5M paid so far, of $30.0M agreed · runs to November 2029
November 1, 2024November 1, 2029
running

Paid to

WSP-PGH Wong Joint Ventureprime contractor$9.5M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Muni transit fund · multi-year projects100%$1.5M

Paid year by year, FY2025–FY2026

FY2026$6.0M
FY2025$1.5M

Type and award

Contract type: Professional services under the City Charter

Award: Competitive bid

Next contract in this departmentMuni train control system work20th of 169 active contracts in this department by amount agreed$29.8M

Contract 1000034898 · Source: Supplier Contracts · every payment on this contract