AN Project Ctrls & CM Services No.3

ECS-SCG JV · DPW Public Works

San Francisco agreed $3.3M with ECS-SCG JV for contract 1000034939 (DPW Public Works); $0 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PW AN Prj Ctrls & CM Svcs No.3

Signed by Public Works

LBE
Agreed
$3.3M
Paid
$0
0% of agreed
Remaining (calculated)
$3.3M
The money
Paid against the agreed amount
Payments per fiscal year

No voucher-level payment detail for this contract (detail begins FY2018 — earlier or indirect payments don’t appear).

Payment detail begins FY2018
The deal
Contract term
December 9, 2024January 23, 2030
Term running
Recorded purchasing authority
Purchasing authority, verbatim
TERM CONTRACT PROFSERV-BID, ENVIRONMENTAL CONSULTING

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
ECS-SCG JVLBEPrime
JOE HILL CONSULTING ENGINEERSLBESubcontractor$660,000
C M PROSLBESubcontractor$396,000
JBR PARTNERS INCLBESubcontractor$44,000
Margena Wade, LLCSubcontractor$44,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)