Skip to main content

Public Works

Project control and construction management 4 (MLBE)

Original title: “PW AN Proj Ctrl & CM 4 (MLBE)” · prime is a certified Local Business Enterprise

$132,150
paid on this contract in FY2025
$2.1M paid so far, more than the $1.9M recorded as agreed · runs to January 2030
December 9, 2024January 23, 2030
running

Paid to

Design & Construction Management Servicesprime contractor$2.1M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Capital projects fund · multi-year projects91%$120,594
San Francisco General Hospital fund · multi-year projects9%$11,556

Paid year by year, FY2025–FY2026

FY2026$1.6M
FY2025$132,150

Type and award

Contract type: Professional services for public works

Award: Competitive bid

The project team

Design & Construction Management ServicesPrime Contractor · LBE
M.D. Construction & Project ManagementSubcontractor · LBE$150,000
AbaSubcontractor · LBE$75,000
M Lee CorporationSubcontractor · LBE$75,000
Microestimating IncSubcontractor · LBE$75,000
Next contract in this departmentPavement renovation and sewer work118th of 282 active contracts in this department by amount agreed$1.9M

Contract 1000034947 · Source: Supplier Contracts · every payment on this contract