Legion of Honor-Cap-BMS Replace Phase 1

PACIFIC COAST TRANE CONTROLS · FAM Fine Arts Museum

San Francisco agreed $203,104 with PACIFIC COAST TRANE CONTROLS for contract 1000035054 (FAM Fine Arts Museum); $182,793 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:FAM-LH-Cap-BMS Replace Phase 1

Signed by Fine Arts Museum

Agreed
$203,104
Paid
$182,793
90% of agreed
Remaining (calculated)
$20,311
The money
Paid against the agreed amount
Payments per fiscal year
26
Largest year: $182,793 · dashed = fiscal year not closed yet
Payment detail begins FY2018
The deal
Contract term
December 4, 2024June 30, 2027
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CHARTER SEC 5.101 AUTHORITY - CHARITABLE TRUST DEPT (AAM,FAM,WAR)