AN Env Consulting Service 2025
TRC SOLUTIONS INC · DPW Public Works
San Francisco agreed $960,000 with TRC SOLUTIONS INC for contract 1000035610 (DPW Public Works); $93,003 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.
Register title: “PW AN Env Cnslt Svc 2025”
Signed by Public Works
These bars total $198,100; the figure above is $93,003. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.
| Supplier | Role | Attached $ |
|---|---|---|
| TRC SOLUTIONS INC | Prime | — |
| A E W ENGINEERING INCLBE | Subcontractor | $375,000 |
| Pacific Legacy, Inc. | Subcontractor | $90,000 |
| APPLIED TECHNOLOGY & SCIENCE A-T-SLBE | Subcontractor | $30,000 |
| AVILA & ASSOC CONSULTING ENGINEERS INCLBE | Subcontractor | $30,000 |
| WILSON, IHRIG & ASSOCIATES, INC. | Subcontractor | $15,000 |
| GROUND PENETRATING RADAR SYSTEMS, LLC | Subcontractor | $0 |
Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.