Skip to main content

Office of Economic and Workforce Development

Downtown pop-up program

Original title: “ECN Downtown PopUp RFP231” · nonprofit contractor

$1.1M
paid on this contract in FY2026
$1.1M paid so far, of $1.5M agreed · runs to December 2026
April 1, 2025December 31, 2026
running

Paid to

SF New Dealprime contractor$1.1M

Paid from, FY2026

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

General Fund · multi-year projects89%$958,000
General Fund · annual projects11%$122,000

Type and award

Contract type: Grants the City gives out

Award: Grant

Next contract in this departmentTechSF On-Ramp grant from Economic and Workforce Development11th of 62 active contracts in this department by amount agreed$1.4M

Contract 1000035708 · Source: Supplier Contracts · every payment on this contract