Main Street improvements phase one for Public Works

Original title: “PW MAIN STREET IMPR PHASE I” · prime is a certified Local Business Enterprise

$276,327
paid on this contract in FY2026
$276,327 paid so far, of $6.0M agreed · runs to September 2027
July 24, 2025September 13, 2027
running

Paid to

Bay Area Lightworks Incprime contractor$276,327

Paid from, FY2026

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Capital projects fund100%$276,327

Type and award

Contract type: Construction

Award: Competitive bid

The project team

Bay Area Lightworks IncPrime Contractor · LBE
Bauman Landscape & Construction IncSubcontractor · LBE$1.4M
Basset EngineeringSubcontractor · LBE$976,807
Reliance Engineering IncSubcontractor · LBE$302,100
Esquivel Grading & Paving IncSubcontractor · LBE$205,041
DR Traffic ControlSubcontractor · LBE$200,000
Catmex MaintenanceSubcontractor · LBE$55,709
Apex Testing Laboratories IncSubcontractor · LBE$50,000
ABM Electrical Power Services, LLCSubcontractor$32,560
Next contract in this departmentSafer Taylor Street project32nd of 282 active contracts in this department by amount agreed$6.0M