Fine Arts Museums

Equipment work at the Legion of Honor museum

Original title: “FAM-LH-Cap-Vacuum Condensate s”

$65,546
paid on this contract in FY2026
$65,546 paid so far, of $65,546 agreed · runs to June 2027
September 15, 2025June 30, 2027
running

Paid to

Bay City Boiler & Engineering Co Incprime contractor$65,546

Paid from, FY2026

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

General Fund · multi-year projects100%$65,546

Type and award

Contract type: Rents and other non-purchase agreements

Award: Charter section 5.101 authority - charitable trust department (AAM,FAM,WAR)