Brannan Street outfall improvements for Public Utilities Commission

Original title: “PUC Brannan St Outfall Imprvmt” · prime is a certified Local Business Enterprise

$583,153
paid on this contract in FY2026
$641,103 paid so far, of $3.2M agreed · runs to January 2027
January 5, 2026January 18, 2027
running

Paid to

R&S Construction Management Incprime contractor$641,103

Paid from, FY2026

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Wastewater fund100%$583,153

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

R&S Construction Management IncPrime Contractor · LBE
Baytech Engineering, Inc.Subcontractor · LBE$480,000
Next contract in this departmentRoof coating construction for the Public Utilities Commission215th of 493 active contracts in this department by amount agreed$3.1M

Contract 1000037745 · Source: Supplier Contracts · every payment on this contract