Skip to main content

Public Utilities Commission

Sansome Street outfall improvements for Public Utilities Commission

Original title: “PUC Sansome St Outfall Imprvmt”

$420,673
paid on this contract in FY2026
$729,043 paid so far, of $2.9M agreed · runs to November 2027
January 27, 2026November 22, 2027
running

Paid to

R&S Construction Management Incprime contractor$729,043

Paid from, FY2026

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Wastewater fund · multi-year projects100%$420,673

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

R&S Construction Management IncPrime Contractor
Baytech Engineering, Inc.Subcontractor · LBE$749,750
Next contract in this departmentTransmission pipe construction at various locations, phase two220th of 493 active contracts in this department by amount agreed$2.9M

Contract 1000037865 · Source: Supplier Contracts · every payment on this contract