Skip to main content

Public contracts of the Charente département · 2025

Liaison RD736 / RD939 à Rouillac-1 ère tranche

€1.2M
contract ceiling — what was paid on it is not published
Signed on 5 March 2025 · ended around April 2026 · 13 months

Who won it

Eurovia Poitou Charentes LimousinConstruction de routes et autoroutes · registered office Limoges (87000) · headcount 500 to 999 employees · SIREN 412395709

Number 8 by amount of the 197 contracts the Charente département published for 2025.

Other contracts of Eurovia Poitou Charentes Limousin in Charente

Fourniture, transport et mise en oeuvre de matériaux traités aux liants…202624€MRD674 Aménagement de la traverse de Montboyer2026415€kRD 6-Aménagement des traverses de Lavaud et Monthézard…2026239€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 11

Subcontracting declared : yes

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.