RD20 aménagement traverse clerlande

€122k
maximum contract amount over 5 months — what was paid on it is not published
Signed on 24 September 2024 · ended around February 2025 · 5 months

Who won it

Eurovia Drome Ardeche Loire AuvergneConstruction de routes et autoroutes · registered office Saint-Jean-Bonnefonds (42650) · headcount 500 to 999 employees · SIREN 317975910

Number 106 by amount of the 176 contracts the Puy-de-Dôme département published for 2024.

Other contracts of Eurovia Drome Ardeche Loire Auvergne in Puy-de-Dôme

Travaux d’aménagement en traverse d’agglomération Effiat2026 · maximum over 8 months697€kTravaux aménagement en traverse d’agglomération effiat2026 · maximum over 6 months345€kRD8 Travaux aménagement traverse Tallende2025 · maximum over 4 months219€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Unitaire

Published amendments : 2

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.