Public contracts of the Vosges département · 2023

Reconstruction des ateliers du centre d’exploitation principal de neufchateau

Charpente métallique

€155k
contract ceiling — what was paid on it is not published
Signed on 6 June 2023 · ended around March 2024 · 9 months

Who won it

AuerSIREN 881188809

Number 104 by amount of the 190 contracts the Vosges département published for 2023.

Other contracts of Auer in Vosges

Reconstruction des ateliers du centre d’exploitation principal de…2025155€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Révisable

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.

Reconstruction des ateliers du centre d’exploitation principal de…: €155k, Vosges 2023 · Qipu