Skip to main content

Public contracts of Bordeaux Métropole · 2021

Maîtrise d’œuvre travaux sur les ouvrages de protection contre les inondations fluviomaritimes Ambes

€1.6M
framework agreement: a maximum envelope for orders over 4 years, not spending — what was paid on it is not published
Signed on 28 July 2021 · ended around July 2025 · 4 yrs

That is at most ~€390k a year on average: a maximum too.

Who won it

Setec HydratecIngénierie, études techniques · registered office Paris (75012) · headcount 200 to 249 employees · SIREN 301392569

A contract awarded to 2 holders; above, the main holder. With it: Terrasol. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

3 bids received

Median for this procedure in 2021: 6 bids, across 1797 comparable contracts. Open tender · awarded to 2 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 37 by amount of the 124 contracts Bordeaux Métropole published for 2021.

Other contracts of Setec Hydratec in Bordeaux Métropole

Maîtrise d’oeuvre pour les travaux sur les ouvrages de protection…2025 · maximum over 5 years870€kAssistance à maîtrise d’ouvrage pour la réalisation d’études…2023 · maximum over 12 months2.8€MAssistance à maîtrise d’ouvrage2020 · maximum over 3 months36€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Framework agreement : yes: orders follow, the amount is a ceiling

Price : Forfaitaire

Published amendments : 1

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.