Public contracts of Communauté d'agglomération Cholet Agglomération · 2021
Maîtrise d’œuvre pour la construction d’une STEP a maulevrier
€185k
contract ceiling — what was paid on it is not published
Who won it
Philippe Bossard Architecte DPLGSIREN 449445337Main holder, with the largest amount. The contract has 3 holders; the others are not shown here yet.
Number 67 by amount of the 155 contracts Communauté d'agglomération Cholet Agglomération published for 2021.
Other contracts of Philippe Bossard Architecte DPLG in Communauté d'agglomération Cholet Agglomération
Maîtrise d’œuvre pour la construction d’une station d’épuration a…2025174€kMaîtrise d’œuvre pour la construction d’une station d’épuration a…2020157€kContract details (procedure, price, amendments, lots)
Procedure : Appel d'offres ouvert
Price : Révisable
Published amendments : 2
Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.