Construction d’une école relai en bâtiments modulaires sur la Ville de Creil

Gros oeuvre et fondations

€943k
contract ceiling — what was paid on it is not published
Signed on 29 October 2025 · running until about March 2027 · 17 months
Ongoing30 Mar 2027

Who won it

Modern Construction BâtimentTravaux de maçonnerie générale et gros œuvre de bâtiment · registered office Noisy-Le-Sec (93130) · headcount 6 to 9 employees · SIREN 849734926

The competition

5 bids received

Median for this procedure in 2025: 3 bids, across 17695 comparable contracts. Open tender · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 5 by amount of the 70 contracts Communauté d'agglomération Creil Sud Oise published for 2025.

Other contracts of Modern Construction Bâtiment in Communauté d'agglomération Creil Sud Oise

Construction d’une école relai en bâtiments modulaires…2024943€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : 2

Subcontracting declared : no

Social considerations : Clause sociale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.