Skip to main content

Public contracts of Communauté d'agglomération de Haguenau · 2020

Haguenau : travaux de renouvellement du réseau d’eau potable

Rue de la Coudraie

€69k
maximum contract amount over 3 years — what was paid on it is not published
Signed on 25 May 2020 · ended around May 2023 · 3 yrs

That is at most ~€23k a year on average: a maximum too.

Company selected

Artere Construction et TP SudTravaux de terrassement courants et travaux préparatoires · registered office Marlenheim (67520) · headcount 20 to 49 employees · SIREN 794418582

The competition

16 bids received

awarded to 1 company

Open data gives the contract holder and the number of bids. The identity of unsuccessful bidders is not published.

Number 50 by amount of the 91 contracts Communauté d'agglomération de Haguenau published for 2020.

Other contracts of Artere Construction et TP Sud in Communauté d'agglomération de Haguenau

Travaux sur collecteurs d’eaux usées et d’eaux pluviales…2024 · maximum over 4 years3.2€MTravaux de gestion des eaux pluviales et d’aménagements paysagers à la…2024 · maximum over 4 years460€kCommunauté d'agglomération de Haguenau2024 · maximum over 3 months178€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.