Public contracts of Communauté d'agglomération de Haguenau · 2022

Schirrhein : Construction d’un accueil périscolaire

Voirie aménagements extérieurs

€98k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 23 December 2022 · ended around March 2024 · 15 months

That is at most ~€79k a year on average: a maximum too.

Who won it

Willem Routes et Travaux PublicsTravaux de terrassement courants et travaux préparatoires · registered office Schweighouse-Sur-Moder (67590) · headcount 20 to 49 employees · SIREN 792643587

The competition

58 bids received

awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 100 by amount of the 200 contracts Communauté d'agglomération de Haguenau published for 2022.

Other contracts of Willem Routes et Travaux Publics in Communauté d'agglomération de Haguenau

Travaux renforcement du réseau d’eau potable rue de la république…2026 · maximum over 2 months108€kRenforcement du réseau d’eau potable rue de l’hiver a oberhoffen…2026 · maximum over 5 months88€kSchweighouse sur moder travaux de restructuration…2026 · maximum over 13 months69€k
Contract details (procedure, price, amendments, lots)

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.