Public contracts of Communauté urbaine de Dunkerque · 2025

Maîtrise d’œuvre pour la construction de la passerelle ile jeanty

€595k
maximum contract amount over 4 years — what was paid on it is not published
Signed on 17 March 2025 · running until about December 2028 · 4 yrs
Ongoing16 Dec 2028

That is at most ~€159k a year on average: a maximum too.

Who won it

Cre-Ingenierie Bureau d'ÉtudesIngénierie, études techniques · registered office Dunkerque (59240) · headcount 6 to 9 employees · SIREN 379461973

A contract awarded to a consortium of 6 holders; above, the main holder. With it: D.V.V.D Ingenieurs, On, DVVD Architectes, Cre-Ingenierie Opc & Maitrise d'Oeuvre (Creiom), Oxymore Architectes. The amount is the whole contract’s: the DECP does not publish each holder’s share.

Number 45 by amount of the 243 contracts Communauté urbaine de Dunkerque published for 2025.

Other contracts of Cre-Ingenierie Bureau d'Études in Communauté urbaine de Dunkerque

Maîtrise d’œuvre réalisation sanitaires kursaal2022 · maximum over 2 years54€kMaîtrise d’oeuvre pour la rénovation du plus2021 · maximum over 22 months88€kMaîtrise d’oeuvre pour la rénovation de l’étanchéité de la toiture…2021 · maximum over 12 months77€k
Contract details (procedure, price, amendments, lots)

Procedure : Marché passé sans publicité ni mise en concurrence préalable

Price : Mixte

Published amendments : 1

Subcontracting declared : no