Public contracts of Communauté urbaine de Dunkerque · 2022

Maîtrise d’œuvre réalisation sanitaires kursaal

€54k
maximum contract amount over 2 years — what was paid on it is not published
Signed on 5 December 2022 · ended around January 2025 · 2 yrs

That is at most ~€26k a year on average: a maximum too.

Who won it

Cre-Ingenierie Bureau d'ÉtudesIngénierie, études techniques · registered office Dunkerque (59240) · headcount 6 to 9 employees · SIREN 379461973

A contract awarded to a consortium of 4 holders; above, the main holder. With it: Cre-Ingenierie Opc & Maitrise d'Oeuvre (Creiom), Savreux Sanitation. The amount is the whole contract’s: the DECP does not publish each holder’s share.

The competition

2 bids received

Median for this procedure in 2022: 3 bids, across 2458 comparable contracts. Simplified procedure · awarded to 4 companies

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 201 by amount of the 254 contracts Communauté urbaine de Dunkerque published for 2022.

Other contracts of Cre-Ingenierie Bureau d'Études in Communauté urbaine de Dunkerque

Maîtrise d’œuvre pour la construction de la passerelle ile jeanty2025 · maximum over 4 years595€kMaîtrise d’oeuvre pour la rénovation du plus2021 · maximum over 22 months88€kMaîtrise d’oeuvre pour la rénovation de l’étanchéité de la toiture…2021 · maximum over 12 months77€k
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Mixte

Published amendments : 1