Public contracts of Toulouse Métropole · 2023

Travaux d’assainissement

Reconstruction du poste de refoulement saint sauveur et pose du réseau de transfert en forage dirige

€519k
maximum contract amount over 8 months — what was paid on it is not published
Signed on 28 August 2023 · ended around April 2024 · 8 months

Who won it

SubterraConstruction de réseaux pour fluides · registered office Portet-Sur-Garonne (31120) · headcount 20 to 49 employees · SIREN 481442762

The competition

5 bids received

Median for this procedure in 2023: 3 bids, across 8300 comparable contracts. Simplified procedure · awarded to 1 company

Open data publishes the winner and the bid count — never the identity of unsuccessful bidders.

Number 64 by amount of the 162 contracts Toulouse Métropole published for 2023.

Other contracts of Subterra in Toulouse Métropole

Travaux d’assainissement d’eaux usées2023 · maximum over 7 months1.2€MBlagnac et Toulouse travaux dassainissement EU2023 · maximum over 10 months1.1€MTravaux de réhabilitation des réseaux EU et EP sur le territoire de TM2022 · maximum over 5.5 years26.1€M
Contract details (procedure, price, amendments, lots)

Procedure : Adapted procedure: the lighter procedure allowed under the EU thresholds

Price : Forfaitaire

Published amendments : none

Subcontracting declared : no

Social considerations : Critère social, Clause sociale, Marché réservé

Environmental considerations : Critère environnemental, Clause environnementale

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.