Skip to main content

Public contracts of Meudon · 2025 · Construction and buildings

A rénovation et extension de l’école élémentaire ferdinand buisson

Menuiseries extérieures métalliques

€207k
maximum contract amount over 15 months — what was paid on it is not published
Signed on 23 May 2025 · ended around August 2026 · 15 months

That is at most ~€166k a year on average: a maximum too.

Company selected

EriTravaux d'installation électrique dans tous locaux · registered office Fontenay-Sous-Bois (94120) · headcount 500 to 999 employees · SIREN 572078905

Number 49 by amount of the 102 contracts Meudon published for 2025. It belongs to the policy Schools.

Other contracts of Eri in Meudon

Restauration et aménagement de la chapelle saint-georges2023 · maximum over 14 months10€kPlomberie chauffage ventilation rénovation gs le val phase 12021 · maximum over 6 months45€kRénovation du groupe scolaire LE VAL2021 · maximum over 3 months42€k
Contract details (procedure, price, amendments, lots)

Procedure : Appel d'offres ouvert

Price : Forfaitaire

Published amendments : none

Contracts above €40,000 excluding VAT, as declared when they are awarded (DECP): contract amounts, not payments. Smaller contracts are not published; obviously wrong amounts are set aside.