In 2022, the City of Paris budgeted €61k for "Charlotte Delbo Library - Stairwell refurbishment" ().
Source: City of Paris, localised investments in the administrative account, data as of 9 February 2026.
61k €
voted in the 2022 budget
Renovation of the Charlotte Delbo Library staircase. Full refurbishment of the building's stairwell. The works will renew the steps and walls to improve the welcome of the public.
Library · Other
Contracts on this project
Matched automatically: check each contract’s purpose.
Lot 3 Travaux Réalisation Pose Escalier Metallique Paris 18EMAteliers Bois et Compagnie · 2022 · confirmed606k €Réfection Escalier à EM 52 Turenne 3E lot 2 Charpente BoisBepox · 2022 · confirmed155k €Études pour rénover un escalier, installer des stores et ajouter des plantesMbap · 2024 · confirmed80k €Lot 3 Travaux Réfection Escalier à EM 52 Turenne Paris 3EAtelier Philippe D Art · 2022 · confirmed78k €Travaux de Fourniture et Pose de Garde-corps et un Escalier 14ÈMEtancheco · 2021 · confirmed48k €Other library projects · 2022
Batignolles Library redesigned and made accessible17th150k €Charlotte Delbo Library extension106k €Amount voted, not final spending. Source: Administrative account appendix 2022 · page 9 ↗