5th district Town Hall - Safety-accessibility master plan
In 2022, the City of Paris budgeted €851k for "5th district Town Hall - Safety-accessibility master plan" (, 5th arrondissement).
Source: City of Paris, localised investments in the administrative account, data as of 9 February 2026.
851k €
voted in the 2022 budget
Works to make the town hall more accessible and secure. Disabled-access equipment and safety-system upgrades. The administrative building is brought up to current public-welcome standards.
Administration · Other
Contracts on this project
Matched automatically: check each contract’s purpose.
Travaux Mise en Sécurité/accessibilité Mairie 5e lot 1GM Bâtiment de France 1 · 2019 · confirmed2€MLot 3 Deconstruct. pour Mesures Sécurité BatimentaireTersen · 2022 · confirmed800k €Maintenance Equipts Sécurité des Stations Assainn lot 2Spie Facilities · 2022 · confirmed400k €Journal D'arrondissement du 5e-2022SARL Cithea Communication · 2022 · confirmed135k €Métropole du Grand Paris assistance à maîtrise d’ouvrage Schema Directeur Energetique Pilotage Démarche lot 1Algoe · 2019 · confirmed81k €Other administration projects · 2022
Day-care centre Garancière - Restructuring works6th907k €11th district Town Hall - Facade refurbishment and roofing11th860k €Window frames, attic insulation, floor refurbishment, Town Hall facade refurbishment20th759k €(waterproofing works)12th453k €Arrondissement 5 · View on OpenStreetMap ↗
Amount voted, not final spending. Source: Administrative account appendix 2022 · page 12 ↗