Nursery School 31 rue Château des Rentiers - Asbestos removal in two stairwells
In 2022, the City of Paris budgeted €131k for "Nursery School 31 rue Château des Rentiers - Asbestos removal in two stairwells" (, 13th arrondissement).
Source: City of Paris, localised investments in the administrative account, data as of 9 February 2026.
Asbestos removal in the stairwells of the Château des Rentiers Nursery School. Targeted asbestos-removal works on the building's two stairwells. The intervention secures the school's interior circulation structures.
School · Other
Contracts on this project
Matched automatically: check each contract’s purpose.
Lot 1 Demolition/desamiantage CS Poissonniers JO 2024Edile Construction · 2022 · confirmed1.4€MTravaux Desamiantage Deplomb. Centre Sportif MAX Rousie lot 1Premys · 2022 · confirmed696k €Lot 3 Travaux Réalisation Pose Escalier Metallique Paris 18EMAteliers Bois et Compagnie · 2022 · confirmed606k €Travaux Desamiantage et Aménagement Refectoire COL MeliesDMW · 2022 · confirmed295k €Modernisation du système de sécurité incendie du centre sportif Château des Rentiers.Phonelec · 2024 · confirmed · 3 bids received68k €Other school projects · 2022
Primary School A 53 rue Baudricourt - Kitchen and dining-hall upgrade13th5.3€MPrimary School 73/75 boulevard Davout - Construction of 10 classrooms20th4.8€MZAC Saint-Vincent-de-Paul - School creation14th1.8€MIndividual operations - Nursery School 12 cité Souzy - Kitchen renovation11th1.2€M31 Rue du Château des Rentiers 75013 Paris · View on OpenStreetMap ↗
Amount voted, not final spending. Source: Administrative account appendix 2022 · page 38 ↗