Halle Pajol

Halle Pajol (public facility, 18th arrondissement): €101k paid by the City in 2019 and 9 Paris Council deliberations about it. The source of each item is given.

Source: Conseil de Paris, Bulletin municipal officiel, opendata.paris.fr, data as of 29 September 2026.

€101k
paid by the City for this place in 2019

The ZAC Pajol is a concerted development zone (zone d'aménagement concerté) located on rue Pajol in the heart of the La Chapelle neighbourhood. Wikipedia ↗

One of 225 places · €2.9 B paid by the City

What the City funds here

Outside the figure: €1.7 M of works and renovation, in 2009. The City publishes investment from 2009, subsidies from 2010.

At the Conseil de Paris

4 moments chosen from the 9 deliberations about this place.

JULY 2020Transfer to Enercoop of the electricity resale contract debatedThe transfer to Enercoop of the electricity resale contract is debated: Mr Jean-Noël Aqua (Communist and Citizen group) states “we are not convinced by this draft deliberation” and considers the public service “better placed to respond to the challenges at stake”; according to Mr Jacques Baudrier, the plant “was commissioned in 2013”.Read the decision ↗
FEBRUARY 2012Delivery announced for late 2012; solar-panel contractor withdrawsMs Frédérique Pigeon states that “the hall will be delivered at the end of 2012” with a youth hostel and gardens; on a UMPPA motion, the deputy mayor speaking on behalf of the 8th Committee asserts that the company with which the commitment on the hall's photovoltaic panels had been finalized following a call for tenders “had to withdraw”.Read the decision ↗
MAY 2008Design contract awarded to Jourda ArchitectesThe Council approves the award of the design and construction supervision contract to JOURDA Architectes Paris, in association with ECO CITE and IN SITU, and authorizes the Mayor to sign this contract and to file the applications for demolition and building permits.Read the decision ↗
DECEMBER 2007Renovation and new public garden approvedThe Council approves the principle of works to rehabilitate the hall and create a public garden, as well as the award of five intellectual services contracts.Read the decision ↗
3 more moments, 2003–2010
MARCH 2010Works contract terms approved; amendment No. 1 to the joint purchasing agreementThe Council approves the award procedures for the works contracts and authorizes the Mayor to sign amendment No. 1 to the joint procurement agreement.Read the decision ↗
MAY 2008Building's energy design praised in the council sessionMr Yves Contassot welcomes, during the session, the choice to entrust the rehabilitation of the hall to Hélène Jourda, considering that “we are doing much better than the Climate Plan in terms of energy efficiency and design”.Read the decision ↗
DECEMBER 2003'Parquet Pajol' project approved; €60,000 grant requestedThe Council approves the principle of the “Parquet Pajol” operation, Halle Pajol sector, and authorizes the Mayor to apply for a regional grant, expected revenue: 60,000 euros.Read the decision ↗

All deliberations ↗

Other places · Squares & monuments