Original title: “HHWP POWER TRNSM LINE CLRNC MI”
$94,125
paid on this contract in FY2025
April 4, 2017April 3, 2027
Paid to, since FY2018
Black & Veatch Corporationprime contractor$722,267Paid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Hetch Hetchy power fund · multi-year projects$67,388
Hetch Hetchy power fund$26,737
Paid year by year, FY2021–FY2026
$265,003 in FY2021 · $272,988 in FY2022 (the highest) · $45,928 in FY2026
Click a year to see its amount.
Payment detail begins FY2018 ⓘ
Type and award
Contract type: Professional services for public works
Award: Competitive bid
The project team
Black & Veatch CorporationPrime ContractorVista Connections Inc.Subcontractor$300,000
Win Structural Consulting GRP, Inc.Subcontractor$300,000
Geotechnical Consultants IncSubcontractor · LBE$150,000
Pacific Engineering & Construction IncSubcontractor$150,000
Contract 1000000327 · Source: Supplier Contracts · every payment on this contract