Skip to main content

Public Utilities Commission

Replacing the Calaveras Dam

Original title: “PUC CALAVERAS DAM REPLAC PROJ”

$1.7M
paid on this contract in FY2020
$95.2M paid since FY2018, of $561.0M on file as agreed since July 2017 · ended July 2019

Paid to, since FY2018

Dragados USA/Flatiron West/Sukut Construction JVprime contractor$95.2M

Paid from, FY2020

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Water fund100%$1.7M

Paid year by year, FY2018–FY2020

$51.3M in FY2018 · $1.7M in FY2020

Click a year to see its amount.

Payment detail begins FY2018 ⓘ

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

Dragados USA/Flatiron West/Sukut Construction JVPrime Contractor
Tom Mayo ConstructionSubcontractor$26.1M
Western Steel Erectors IncSubcontractor$3.7M
Sti TruckingSubcontractor$3.4M
A1 Protective Services IncSubcontractor · LBE$1.4M
Vacc Inc DBA Vibro-Acoustic ConsultantsSubcontractor · LBE$956,830
City Source Rental & SupplySubcontractor$897,028
Karlas Janitorial ServicesSubcontractor · LBE$358,811
CMC Traffic Control Specialists LLCSubcontractor · LBE$119,604

Contract 1000000502 · Source: Supplier Contracts · every payment on this contract