Qipu

CMGC ACC Facility&Burke Whouse

CLARK CONSTRUCTION GROUP - CALIF LP · DPW GSA - Public Works

San Francisco agreed $92.4M with CLARK CONSTRUCTION GROUP - CALIF LP for contract 1000000927 (DPW GSA - Public Works); $94.4M has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:PW CMGC ACC Fac&Burke Whouse

Signed by GSA - Public Works

Agreed
$92.4M
Paid
$94.4M
more than the recorded base
Remaining (calculated)
$0
The money
Paid against the agreed amount

$94.4M paid · $2.0M more than the recorded base amount · Agreed $92.4M

Payments per fiscal year
1819202122
Largest year: $33.5M
Payment detail begins FY2018
The deal
Contract term
May 8, 2017March 31, 2021
Term ended
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICES

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
CLARK CONSTRUCTION GROUP - CALIF LPPrime
DABRI INCSubcontractor$655,491
JBR PARTNERS INCLBESubcontractor$655,491
MERRIWETHER & WILLIAMS INSURANCE SVC INCLBESubcontractor$655,491

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.