Original title: “PUC TI WWTP RECYCLE ENG SVCS”
$64,503
paid on this contract in FY2025
April 18, 2018December 17, 2026
Paid to
Carollo Engineers PCprime contractor$5.2MPaid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.
Wastewater fund$64,503
Paid year by year, FY2019–FY2026
$535,171 in FY2019 · $2.7M in FY2020 (the highest) · $29,072 in FY2026
Click a year to see its amount.
Type and award
Contract type: Professional services for public works
Award: Competitive bid
The project team
Carollo Engineers PCPrime ContractorCH2M Hill Engineers IncSubcontractor$2.0M
Freyer & Laureta IncSubcontractor · LBE$352,800
Geotechnical Consultants IncSubcontractor · LBE$216,000
CMG Landscape ArchitectureSubcontractor · LBE$72,000
Avila & Assoc Consulting Engineers IncSubcontractor · LBE$30,000
Environmental Science Associates IncSubcontractor$24,000
Contract 1000009699 · Source: Supplier Contracts · every payment on this contract