Skip to main content
Qipu

40201-1819-AS ND CM -Swin

SWINERTON BUILDERS · REC Recreation & Park Commsn

San Francisco agreed $987,500 with SWINERTON BUILDERS for contract 1000015811 (REC Recreation & Park Commsn); $248,838 has been paid on it so far. Source: SF Controller supplier contracts (open data), data as of 13 July 2026.

Register title:REC-40201-1819-AS ND CM -SWIN

Signed by Recreation & Park Commsn

Agreed
$987,500
Paid
$248,838
25% of agreed
Remaining (calculated)
$738,662
The money
Paid against the agreed amount
Payments per fiscal year
20212223242526
Largest year: $231,566 · dashed = fiscal year not closed yet

These bars total $560,618; the figure above is $248,838. The first comes from the City’s payment ledger, the second from the contract register’s own paid column. They match on ordinary contracts and drift apart on multi-phase projects, where the work runs through several purchase orders and the ledger counts all of them.

Payment detail begins FY2018
The deal
Contract term
August 29, 2019January 9, 2028
Term running
Recorded purchasing authority
Purchasing authority, verbatim
CONSTRUCTION SERVICES

See every contract awarded under Competitive bid →

Project team
SupplierRoleAttached $
SWINERTON BUILDERSPrime
M LEE CORPORATIONSubcontractor$350,000
MERCURIAL CONSULTINGSubcontractor$168,750
MICROESTIMATING INCLBESubcontractor$168,750
CONSOLIDATED ENGINEERING LABORATORIESSubcontractor$25,000

Attached amounts for subcontractors and JV members live inside the prime's envelope — they are context, never additive with the contract's own amounts.

Sources
This contract in the source
Raw rows (JSON, data.sfgov.org)