Skip to main content

Public Utilities Commission

As-needed electrical and construction work for the water utility

Original title: “PUC AS-NEEDED ELEC & CONSTR SP”

$4.2M
paid on this contract in FY2025
$9.1M paid so far, of $16.6M agreed · runs to January 2028
January 3, 2023January 8, 2028
running

Paid to

VIP Powerline Corpprime contractor$9.1M

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Hetch Hetchy power fund · operating61%$2.6M
Hetch Hetchy power fund17%$695,978
Hetch Hetchy power fund · multi-year projects16%$657,317
Hetch Hetchy power fund · annual projects6%$250,310

Paid year by year, FY2023–FY2026

$661,785 in FY2023 · $4.2M in FY2025 (the highest) · $1.6M in FY2026

Click a year to see its amount.

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

VIP Powerline CorpPrime Contractor
AAES IncSubcontractor · LBE$696,000
FabTech Solar SolutionsSubcontractor$0
Next contract in this departmentAgreement with an irrigation district, 2023–202767th of 493 active contracts in this department by amount agreed$16.5M

Contract 1000027959 · Source: Supplier Contracts · every payment on this contract