Original title: “PW FOLSOM STRTSCP PRJ”
$9.5M
paid on this contract in FY2025
November 3, 2023December 15, 2026
Paid to
Mitchell Engineeringprime contractor$32.5MPaid from, FY2025
The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. A special revenue fund holds money earmarked for a purpose, often grants. The fund does not say where the money first came from.
Sustainable Streets fund$5.0M
Wastewater fund · multi-year projects$3.7M
Muni transit fund · multi-year projects$727,042
Special revenue fund · multi-year projects$30,510
Paid year by year, FY2025–FY2026
FY2026$18.0M
FY2025$9.5M
Type and award
Contract type: Construction
Award: Competitive bid
The project team
Mitchell EngineeringPrime ContractorBay Area Lightworks IncSubcontractor$9.0M
Roadway Construction IncSubcontractor · LBE$3.2M
R&S Construction Management IncSubcontractor · LBE$2.8M
Reliance Engineering IncSubcontractor · LBE$1.6M
Sak Construction LLCSubcontractor$882,800
Lone Star Landscape, Inc.Subcontractor · LBE$748,421
Nor-Cal Pipeline ServicesSubcontractor$497,800
The 4 other team members
Asphalt Impressions IncSubcontractor$325,147
European Paving Designs, Inc.Subcontractor$323,866
MC Metal IncSubcontractor$47,700
Robotic Sewer Solutions, Inc.Subcontractor$45,000
Contract 1000031384 · Source: Supplier Contracts · every payment on this contract