Phase 4 water improvements for Public Utilities Commission

Original title: “PUC BCTD Phase 4 & WTR Improvm” · prime is a certified Local Business Enterprise

$3.0M
paid on this contract in FY2025
$12.9M paid so far, of $15.1M agreed · runs to December 2026
August 9, 2024December 10, 2026
running

Paid to

Mitchell Engineeringprime contractor$12.9M

Paid year by year, FY2025–FY2026

FY2026$9.2M
FY2025$3.0M

Type and award

Contract type: Construction marked “unilateral”

Award: Competitive bid

The project team

Mitchell EngineeringPrime Contractor · LBE
Roadway Construction IncSubcontractor · LBE$611,200
Camajani TruckingSubcontractor · LBE$600,000
On the Level ConcreteSubcontractor · LBE$239,500
R&S Construction Management IncSubcontractor · LBE$180,850
Res Engineers IncSubcontractor · LBE$150,000
DR Traffic ControlSubcontractor · LBE$100,000
Next contract in this departmentEngineering for Lower Alemany storm improvements73rd of 493 active contracts in this department by amount agreed$14.9M