As-needed energy engineering services, Public Utilities Commission

Original title: “PUC/As-Needed Energy EngConSrv”

$30,994
paid on this contract in FY2025
$58,694 paid so far, of $2.4M agreed · runs to July 2029
July 16, 2024July 15, 2029
running

Contractor

Thornton Tomasetti Inc

Paid from, FY2025

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Hetch Hetchy power fund · annual projects100%$30,994

Paid year by year, FY2025–FY2026

FY2026$24,931
FY2025$30,994

Type and award

Contract type: Professional services for public works

Award: Competitive bid

The project team

Thornton Tomasetti IncPrime Contractor
Syska Hennessy GroupSubcontractor$1.0M
Energy Conservation OptionsSubcontractor$200,000
GRD Energy IncSubcontractor · LBE$200,000
Hollins Consulting IncSubcontractor · LBE$200,000
Next contract in this departmentRegion GWTR storage and recovery235th of 493 active contracts in this department by amount agreed$2.4M