Skip to main content

Public Utilities Commission

As-needed engineering design for the Public Utilities Commission

Original title: “PUC AS-NEEDED ENGINR DESIGN SV”

$81,200
paid on this contract in FY2026
$253,830 paid so far, of $5.2M agreed · runs to July 2030
July 2, 2025July 1, 2030
running

Paid to

Catalyst Consulting Group Incprime contractor$253,830

Paid from, FY2026

The fund tells which City account paid. Enterprise funds (Airport, Muni, Water…) are mostly paid from their own fees, fares and rents; the General Fund is mostly local taxes. The fund does not say where the money first came from.

Wastewater fund · multi-year projects79%$64,180
Water fund21%$17,020

Type and award

Contract type: Professional services for public works

Award: Competitive bid

The project team

Catalyst Consulting Group IncPrime Contractor
Bay Area Consulting Engineers IncSubcontractor · LBE$810,000
Next contract in this departmentGas interconnection agreement renewal for Public Utilities Commission166th of 493 active contracts in this department by amount agreed$5.1M